DIAMOND HOUSE- PHASE 2.

DIAMOND HOUSE- PHASE 2. COST ESTIMATE: KES 750,000.
57M2.

COST BREAKDOWN;

DIAMOND HOUSE- PHASE 2. COST ESTIMATE: KES 750,000.

57M2.

COST BREAKDOWN;

MAIN SUMMARY

 
Substructures        150,696.00
 
Reinforced Concrete Frame                     –
 
Superstructure walling          98,201.60
 
Roof structure, covering, finishes and rainwater goods          93,760.00
 
Windows          39,040.00
 
Doors          56,704.00
 
External finishes                     –
 
Floor Finishes          10,780.00
 
Wall Finishes          37,200.00
 
Ceiling Finishes          44,552.00
 
Sanitary Fittings          29,920.00
 
CONSULTANCY FEES                     –
 
Prime Cost and Provisional sums        145,000.00
 
 
Sub Total      705,853.60
 
Technical Support          42,351.22
 

 

CONSULTANCY FEES BREAKDOWN.

Outline proposal        7,500.00
                    –
Scheme design      11,250.00
                    –
Detailed design      15,000.00
Tender action to completion      11,250.00

 

NOTES.

The foundation is based on a4architect.com’s Diamond House technology. This technology reduces costs associated with reinforced concrete by replacing Reinforced concrete in foundations with masonry walling.

In this case, using Reinforced concrete would have costed KES 40,000. Using a4architect.com Diamond technology is estimated at KES 30,000, resulting in a KES 10,000 savings.

The floor is masonry as opposed to the usual reinforced concrete. This results in a further savings of  KES 700 per m2.

Roof.

The roof pitch is as specified in the Diamond House technology.

This represents an estimated cost of KES 13,000 per m2 inclusive of external works and accessories.

Architect Francis Gichuhi Kamau

www.a4architect.com

+254721410684

 

 


Posted

in

by

Tags:

Comments

One response to “DIAMOND HOUSE- PHASE 2.”

  1. pmaina Avatar
    pmaina

    Francis,

    Nice work.I have gone through your analysis to understand your costing and how it would be ideal for me though I feel there are a number of inconsistencies, perhaps you could clarify.

    (a) According to https://www.a4architect.com/diamond-house-plan-cost/ , phase 2 should be 67 meters squared but on this portal it is 57 meters squared. So which is which?
    (b) According to https://www.a4architect.com/diamond-house-plan-cost phase 2 would cost around 1.3M to about 2.3M but your analysis puts construction at 750k.Would you mind clarifying on these costs?
    Thank you in advance.

Leave a Reply to pmainaCancel reply

Verified by MonsterInsights