Earthbag house in Kenya. Construction costs.

Earthbag building currently being constructed at Kiserian, Nairobi.
Cost breakdown.

Foundation. 142 bags=kes 3,000.
Super structure walling.70m2 =kes 21,000
Roofing.kes 22,800.

Floor=kes 30,000
Doors. 2 No. @ kes 5000=kes 10,000
Windows. 2 No. @ kes 2,500=kes 5,000

Wall plaster. =kes 28,000.

Paint=kes 28,000.

Plumbing and electrical works=kes 20,000

TOTAL=KES 167,800.