DIAMOND HOUSE ECO-FRIENDLY PLAN ESTIMATED CONSTRUCTION COSTS
![]() |
| From January 27, 2012 |
A4ARCHITECT.COM DIAMOND ECO-FRIENDLY HOUSE
This house has been designed to offer maximum space use in case the house owner decided to put more units in future.Use of Eco-firendly natural materials such as Stabilised Soil Block walling and natural masonry stone flooring makes the design lower in cost, more aesthetically appealing and friendly to the environment.
For the entrepreneurs at heart, a 1/8th plot can fit 2 Diamond house units each comprising of 3 bedrooms and still leave space for 4 No. car parks.
For those who would like much more privacy, a single Diamond House can be built within the 1/8th acre plot .
PHASED CONSTRUCTION:
The House is designed and implemented in Phases as below:
Phase 0.25: Size: 1 room[bedroom]:area: 10m2: Cost: KES 80,000.
Phase 0.5: Size:1 room[sitting room]:area:32m2:Cost:KES 233,000.
Phase1: Size:Living room,bedroom,bathroom:area:49m2: Cost:KES 980k to KES 1.8m.
Phase 2: Size:Living room,2 bedrooms,bathr.:area:67m2: Cost:KES 1.3 TO 2.3m.
Phase 3: Size:Living room,3 bedrooms,bathr.:area:92m2. Cost:KES 1.8 to 3.2m
BUDGET
The Diamond House is designed to be constructed in Phases.
PHASE 0.25. Plinth Area 10m2.
This phase is Bedroom No.1 in the full Diamond House 3 bedroomed unit.This Phase is best achieved using Interlocking Stabilised Soil blocks since these can be used without internal plaster and paint. The other Phases can then begin to grow from here depending on your budget and space requirements.
See the Cost Breakdown below:
DIAMOND HOUSE PHASE 0.25
|
MAIN SUMMARY |
|
| Substructures | 18,400.00 |
| Reinforced Concrete Frame | - |
| Superstructure walling | 22,494.40 |
| Roof structure, covering, finishes and rainwater goods | 19,464.00 |
| Windows | 4,720.00 |
| Doors | 6,552.00 |
| External finishes | - |
| Floor Finishes | - |
| Wall Finishes | - |
| Ceiling Finishes | - |
| Sanitary Fittings | - |
| - | |
| Design | |
| Prime Cost and Provisional sums | - |
| Sub Total | 71,630.40 |
| Technical Support | 7,163.04 |
| Total Estimate | 78,793.44 |
PHASE 0.5. Plinth Area 35m2.
Phase 0.5-suitable for use with Interlocking Stabilised soil Blocks since this can be used without internal plaster and paint.This Phase has a plinth area of 35m2.
Below is the cost breakdown .
DIAMOND HOUSE PHASE 0.5
35m2
|
MAIN SUMMARY |
|
| Substructures | 48,960.00 |
| Reinforced Concrete Frame | - |
| Superstructure walling | 37,788.80 |
| Roof structure, covering, finishes and rainwater goods | 51,568.00 |
| Windows | 11,680.00 |
| Doors | 32,192.00 |
| External finishes | - |
| Floor Finishes | - |
| Wall Finishes[plaster] | - |
| Ceiling Finishes | - |
| Sanitary Fittings | 29,920.00 |
| - | |
| Design | |
| Prime Cost and Provisional sums | - |
| Sub Total | 212,108.80 |
| Technical Support | 21,210.88 |
| Total Estimate | 233,319.68 |
Phase 0.5 comprises of a Studio bedsitter unit of 35m2.
Phase 1 comprises of 1 bedroomed unit of 49m2.
Phase 2 comprises of 2 bedroomed unit of 57m2.
See construction cost estimates for Phase 2 here.
Phase 3 comprises of 3 bedromed unit of 92 m2.
Phase 1[one bedroomed]can be further constructed in 13 Sub phases broken down as below. This is to enable construction be done in phases that are within the budget.
| DIAMOND HOUSE |
PRICE |
|
KES |
|
| Phase 1-1 bedroomed 49m2. | |
| Ph.1-low cost finishes |
980,000.00 |
| Ph. 1- middle cost finishes |
1,225,000.00 |
| Ph.1-high cost finishes |
1,715,000.00 |
| PHASE 2 | |
| 2 Bedroomed 67m2 | |
| Ph.2-low cost finishes |
1,340,000.00 |
| Ph. 2- middle cost finishes |
1,675,000.00 |
| Ph.2-high cost finishes |
2,345,000.00 |
| PHASE 3 | |
| 3 Bedroomed 92m2 | |
| Ph.3-low cost finishes |
1,840,000.00 |
| Ph. 3- middle cost finishes |
2,300,000.00 |
| Ph.3-high cost finishes |
3,220,000.00 |
COST SAVINGS.
The Diamond House has been designed to utilize all floor space hence reduction of space wasted in circulation such as corridors.
The roof design reduces amount of roof materials and timber required to roof.
The window design reduces the cost of construction further.
The masonry foundation design further reduces a big percentage of the total construction costs.
Architect Francis Gichuhi Kamau
www.a4architect.com
info@a4architect.com
+254721410684
HOW TO MAKE MAXIMUM USE OF A 1/8TH ACRE 50 X 100 PLOT FOR RESIDENTIAL PURPOSES.
The average minimum size of a land subdivision in Kenya, Uganda, Tanzania, Rwanda, Burundi, South Sudan, Somaliland, Botswana, and Senegal is 1/8th acre 50 feet by 100 feet plot size.
![]() |
| From DIAMOND HOUSE V 2.5 |
This plot can be designed to maximize the space. For residential purposes, the plot can be designed to fit in 2 units each comprising of 3 bedrooms with enough car parking for about 4 cars while leaving ample space for a front-yard landscaped garden.
![]() |
| From DIAMOND HOUSE VERSION 2.4 |
For high-rise units on a 50 by 100 feet plot, see here for more details
REASONS TO CONSTRUCT BUNGALOW AS OPPOSED TO HIGH-RISE
![]() |
| From DIAMOND HOUSE V 2.5 |
For plots located in a low-rise residential area, the best option is to construct 2 units within the 50 by 100 feet lot.
- Bungalow type houses carry less weight than the high-rise house types so the foundation costs are greatly reduced.
- Bungalow type houses also do not have the expensive concrete suspended slab so the roofing costs are also greatly reduced.
- It’s easier to construct bungalow houses in phases.
PHASED CONSTRUCTION
The 2 units within the 50 by 100 feet plot can be constructed in phases that suit the owner’s budget.
Each of the 2 units can comprise a complete phase.
Each unit is further divided into 3 phases-phase 1 comprising of 1 bed roomed 49m2, phase 2, two-bed roomed 67m2 and phase 3-three-bedroomed 92m2.
Phase 1[49m2] one bed roomed is further divided into 13 sub-phases as described below:
This way, the Phase 1 can be built slowly using personal savings as per the sub-stages .
Contracts for construction can be made for each particular phase as per the below construction costs.
13 SUB-PHASES OF CONSTRUCTION
|
|
DIAMOND HOUSE BY WWW.A4ARCHITECT.COM |
|||
|
|
||||
|
APPROXIMATE COSTS PER SUB-PHASE |
AMMOUNT -LOW COST FINISHES |
AMMOUNT -MIDDLE COST FINISHES |
AMMOUNT -HIGH COST FINISHES |
|
|
1 |
Substructures[Foundations] | 216,766.44 | 324,198.93 | 431,631.42 |
|
2 |
Reinforced Concrete Frame[Ring beam] | 79,252.80 | 118,531.60 | 157,810.40 |
|
3 |
Superstructure walling-masonry stone | 99,181.82 | 148,337.73 | 197,493.63 |
|
4 |
Roof structure, covering, finishes and rainwater goods-GCI roofing sheets | 86,453.04 | 129,300.38 | 172,147.72 |
|
5 |
Windows-louvre | 44,505.60 | 66,563.20 | 88,620.80 |
|
6 |
Doors | 64,642.56 | 96,680.32 | 128,718.08 |
|
7 |
External finishes | 29,986.56 | 44,848.32 | 59,710.08 |
|
8 |
Floor Finishes-cement screed | 12,289.20 | 18,379.90 | 24,470.60 |
|
9 |
Wall Finishes-plaster on paint | 42,408.00 | 63,426.00 | 84,444.00 |
|
10 |
Ceiling Finishes | 50,789.28 | 75,961.16 | 101,133.04 |
|
11 |
Sanitary Fittings | 34,108.80 | 51,013.60 | 67,918.40 |
|
12 |
project management | 34,627.50 | 51,789.38 | 68,951.25 |
|
13 |
Septic tank, Electrical Wiring,Plumbing | 165,300.00 | 247,225.00 | 329,150.00 |
| Sub Total | 960,311.60 | 1,436,255.51 | 1,912,199.42 | |
| CONSTRUCTION SUPERVSION | 24,007.79 | 35,906.39 | 47,804.99 | |
| Total Estimate | 984,319.39 | 1,472,161.90 | 1,960,004.41 | |
PROFIT/RETURN ON INVESTMENT.
Within the 50 by 100 plot, the2 houses can be constructed for 4 scenarios:
4 SCENARIOS:
A. Both houses for sale
B. Only 1 house for sale while the other is set for owner occupation
C.Only 1 house is set for rental while the other is set for owner occupation
D. Both houses to be rented out.
We will analyze the scenarios here.
ASSUMPTIONS:
- that the land cost is KES 500,000 for a 1/8th plot
-that the a4architect.com Diamond House design is used.
-that the a4architect.com Diamond House Phase 1 –one bed roomed unit [49m2] is constructed
-that interest rate is 20% where borrowing is necessary.
&nb/td/tbody/tdsp;
SCENARIO A-BOTH HOUSES FOR SALE.
This option is good for the entrepreneurial parson who wants to make a quick profit within a short time. Borrowing from Banks is recommended.
| OWNER SELLING BOTH UNITS | ||
| INCLUSIVE OF COST OF BORROWING | ||
| Cost Item |
Kshs |
% |
| Land |
500,000.00 |
11.7837262 |
| Preliminary |
60,000.00 |
1.414047144 |
| Construction |
2,646,000.00 |
62.35947907 |
| External Works |
26,460.00 |
0.623594791 |
| Contingency |
52,920.00 |
1.247189581 |
| Professional fees |
211,680.00 |
4.988758325 |
| Project Management fees |
52,920.00 |
1.247189581 |
| Legal fees |
26,460.00 |
0.623594791 |
| Marketing |
137,500.00 |
3.240524706 |
| Financial Charges[20% of construction cost] |
529,200.00 |
12.47189581 |
| Total |
4,243,140.00 |
100 |
| Financing Plan |
Kshs |
% |
| Developer+a4arcitect.com |
767,200.00 |
18.08094949 |
| Equity Provider |
0.00 |
0 |
| Debt Finance |
2,925,940.00 |
68.95695169 |
| Presales |
550,000.00 |
12.96209882 |
| Total |
4,243,140.00 |
100 |
| PROFIT | ||
| TOTAL SALES FOR 2 UNITS |
5,500,000.00 |
|
| TOTAL EXPENDITURE |
4,243,140.00 |
|
| NET PROFIT |
1,256,860.00 |
|
| NET TAKE-HOME AMMOUNT-profit +land cost |
1,756,860.00 |
|
| PROFIT MARGIN |
29.62098823 |
|
SCENARIO B-ONLY ONE HOUSE IS FOR SALE WHILE THE OTHER IS SET FOR OWNER OCCUPATION.
This option is best for financing owner occupation since the second house finances the construction of the owner occupied house.
The land owner is required to add a small amount [KES 840K] to the investment so as to own his/her own home worth KES 2.74m in the market.
SCENARIO C-ONLY ONE HOUSE IS SET FOR RENTAL WHILE THE OTHER IS SET FOR OWNER OCCUPATION.
This is recommended for those who would like to use their personal savings to construct using 3 no. phases and 13 no. Sub-phases as described above.
The repayment period is 21 years at a rental income of KES 12,000 per month. Rent increases annually so the repayment period will be eventually shortened.
| OWNER RENTING ONLY ONE HOUSE AND LIVING IN THE OTHER | ||
| WITHOUT COST OF BORROWING | ||
| Cost Item |
Kshs |
% |
| Land |
500,000.00 |
14.08458639 |
| Preliminary |
60,000.00 |
1.690150367 |
| Construction |
2,646,000.00 |
74.53563119 |
| External Works |
26,460.00 |
0.745356312 |
| Contingency |
52,920.00 |
1.490712624 |
| Professional fees |
211,680.00 |
5.962850495 |
| Project Management fees |
52,920.00 |
1.490712624 |
| Legal fees |
0.00 |
0 |
| Marketing |
0.00 |
0 |
| Financial Charges[20% of construction cost] |
0.00 |
0 |
| Total |
3,549,980.00 |
100 |
| Financing Plan |
Kshs |
% |
| Developer+a4arcitect.com |
698,450.00 |
19.67475873 |
| Equity Provider |
0.00 |
0 |
| Debt Finance |
2,851,530.00 |
80.32524127 |
| Presales |
0.00 |
0 |
| Total |
3,549,980.00 |
100 |
| PROFIT | ||
| TOTAL SALES FOR 0 UNIT |
0.00 |
|
| TOTAL EXPENDITURE |
3,549,980.00 |
|
| NET PROFIT |
-3,549,980.00 |
|
| NET ADDITIONAL AMMOUNT-profit +land cost |
-3,049,980.00 |
|
| PROFIT MARGIN | ||
| ASSUMED RENTAL INCOME-KES12,000 PER MONTH | ||
| PAY BACK PERIOD |
-254.165 |
-21.18041667 |
| 21 YEARS | ||
| RENTS INCREASE ANNUALY SO THIS TIME WILL BE SHORTENED. | ||
SCENARIO D-BOTH HOUSES RENTED OUT
This scenario is best for the investor who wants to have a low-risk, safe and secure rental property income. The repayment period is 10.5 years. This period will be shortened since rent increases yearly.
| OWNER RENTING BOTH HOUSES | ||
| WITHOUT COST OF BORROWING | ||
| Cost Item |
Kshs |
% |
| Land |
500,000.00 |
14.08458639 |
| Preliminary |
60,000.00 |
1.690150367 |
| Construction |
2,646,000.00 |
74.53563119 |
| External Works |
26,460.00 |
0.745356312 |
| Contingency |
52,920.00 |
1.490712624 |
| Professional fees |
211,680.00 |
5.962850495 |
| Project Management fees |
52,920.00 |
1.490712624 |
| Legal fees |
0.00 |
0 |
| Marketing |
0.00 |
0 |
| Financial Charges[20% of construction cost] |
0.00 |
0 |
| Total |
3,549,980.00 |
100 |
| Financing Plan |
Kshs |
% |
| Developer+a4arcitect.com |
698,450.00 |
19.67475873 |
| Equity Provider |
0.00 |
0 |
| Debt Finance |
2,851,530.00 |
80.32524127 |
| Presales |
0.00 |
0 |
| Total |
3,549,980.00 |
100 |
| PROFIT | ||
| TOTAL SALES FOR 0 UNIT |
0.00 |
|
| TOTAL EXPENDITURE |
3,549,980.00 |
|
| NET PROFIT |
-3,549,980.00 |
|
| NET ADDITIONAL AMMOUNT-profit +land cost |
-3,049,980.00 |
|
| PROFIT MARGIN | ||
| RENTAL INCOME-KES24,000 PER MONTH | ||
| PAY BACK PERIOD |
-127.0825 |
-10.59020833 |
| 10.5 YEARS | ||
| RENTS INCREASE ANNUALY SO THIS TIME WILL BE SHORTENED. | ||
PROCEDURE FOR IMPLEMENTATION OF THE PROJECT.
After the land is acquired, minimum size of 1/8th 50 by 100 feet plot, the above described scenarios can be implemented. This can be done on the 1/8th acre plot and can be increased proportionately to the size of the plot. For example, the project can be increased to 14 units within 1 acre plot, 140 units within a 10 acre plot, and 1400 units within a 1000 acre plot depending on the land size.
STEP 1.
Choose a scenario that best fits your budget or contact www.a4architect.com for assistance on the best scenario for you. You can choose to send email to info@a4architect.com , or visit our offices. Also, choose the cost of finishes that you want for your house i.e. low, middle or high cot finishes as described in the above 13-sub-phases of construction.
STEP 2.
Scan and email to info@a4architect.com the survey plan, mutation plan, deed plan or any survey drawing that has the plot dimensions.
STEP 3.
On receipt of the deed plan, mutation plan or survey plan that shows your plot dimensions, www.a4architect.com will email you the agreement for services as described by the Laws of Kenya.
http://www.a4architect.com/architectural-consulting-service/
STEP 4.
After the agreement is signed, www.a4architect.com will proceed to design the project to the agreed size of land and once through each phase of design, will email soft copies in .pdf format and/or hard copies by Courier service [DHL. Securicor, Wells Fargo, Post Office, e.t.c] to your physical address.
Payments can be delivered through Bank to Bank transfer, Mpesa, Western Union, Money Gram or Cash delivery.
STEP 5.
After receipt of the hard-copy drawings, you can proceed to submit the drawings to the relevant Local Authority for approval. Any changes and recommendations by the local authority is to be reported to us so that we can make the necessary amendments and re-send the documents.
STEP 6.
After local authority approvals, construction contract can be signed and works can commence as per the above described 13-sub phases of construction.
Feel free to contact www.a4architect.com for further information.
Architect Francis Gichuhi Kamau.
+254721410684
tr/strongp align=”right”
%
16 thoughts on “Eco-friendly Hse.”
Leave a Reply
follow:
RSS
Tweet with me






Hi
I am impressed at the pictorial illustrations contained in your website. Could there be any show houses built around Nairobi or Nakuru for viewing? Could the same on the prefab technology? Please let me understand this.
Thanks
Thanks Macharia. There are houses built around Kenya. These are private houses already occupied by the owners .
The early versions of the Diamond House were designed for prefabricated house construction. Read history here
http://www.a4architect.com/2011/10/11/the-growing-house-concept-in-east-africa-diamond-house-by-a4architect-com-from-version-1-0-in-2003-to-version-2-2-in-october-2011/
See a recent design at Kiserian. You can visit the house and respect the owner’s privacy by viewing from outside the compound.
Angalia DIAMOND HOUSE PLAN kwenye ramani kubwa
Greetings,
I learnt about your site through a freind and was very interested. You have done well, my compliments are due.
I just had a few queries I hoped you would answer for me:
1. I an very seriously interested in owning my own house. I have a regular income though quite substantial, so if I took a loan would you make this possibly happen for me?
2. How much would it cost me for a medium cost 4 bedroom house?
3. What is the procedure incase I want to obtain a house using your services?
4. Do you choose everything in terms of the venue, materials and things like that or?
5. How long would it take to build the above mentioned (no. 2) house?
6. I am based in Mombasa, and from your contact us segment I notice that you are based in Nairobi, so would this present any problems/obstacles if we were to “deal” together?
I would really appreciate your clarifications regarding the above matter,
Looking forward to your favorable response,
Thank you.
Hi. Came about your site when surfing for interlocking block designs and have found it very useful. I would like to be able to build using the same in a plot on Kagundo Road and was wondering how you would assist me.
Thanks
@ Maingi. Thanks. To begin your journey to owning your Diamond House, select the Phase you require e.g 0.5,1,2,3 depending on your budget then contact me on info@a4architect.com for the designs , schedule of construction materials and construction supervision.
Happy 2012 to you all..
i have a plot in Utawala opp GSU shooting range size 60*40 and would like to develop some rentals.
- what is your advice on plan etc.
-Options on getting financing considering the land ownership is still in share certificate.
Rgds
Hi Nick.
Check out the feasibility here
http://www.a4architect.com/2011/10/20/development-of-rental-units-on-a-60-x-40-feet-plot-near-main-road/
On share certificate, i dont know of any investors whether individuals or banks who finance based on share certificates. You will have to try personal loan options for this.
Thank you frank for the info.
How many levels are allowed on Utawala Shooting Range area.
Ground + 2 levels. Height is restricted by K.A.A coz of flight path.
Hi Frank
Kudos for creating this very informative/educative site. I have in mind a slightly modified version of the diamond house, I have a few queries though.
1. Would it be viable to use gypsum plasterboard for internal non load bearing walling. Main reason for suggesting this material is to save on labour and material cost but will also ease internal space re-arrangements once all the phases are completed?
2. By what proportion would increasing the plinth area by say between 20 to 30% increase the project cost by?
3. Does your 6% consultancy fee include all other professional fees e.g. quantity surveying, project management?
Thanking you in advance.
Hi Andy,
Thanks for the complements.
1.Gypsum can be used for internal partitions through per m2, its more expensive than stone or stabilized soil block.For ease of space re-arrangements, its perfect.
2.The cost should increase by more or less the same %.
3. 6% is what is recommended minimum under CAP 525 of the laws of Kenya for Architectural services. Other services attract a further cost as per the statute that guides them i.e CAP 530 for structural engineering.
Welcome.
We’ve an 1/8 plot along Thika rd and wish to to develop some residential.
- what is your advice on plan etc.
-Options on getting financing considering the land ownership is still in share certificate.
Cheers
Hi Kimiri,
The number of floors will depend on the demand i.e how close is the plot form Thika road-the closer to Thika road, the higher the building. Financing for plots without title deed is unheard of in the Kenyan banking industry. Unless the banks finance you for a personal loan based on another collateral that has a title then you use the funds to construct.
This is a greater idea but i would love to use stones for either 3 or 4bedroom. can you assist on this? I have 1/8 plot measuring 40ft by 100ft at Kitengela just after Embakasi Ranch sacco plots.May be i can pop into your offices and we discuss more on this. Am interested
Hi Kariuki. Thanks. The design can use any type of walling material e.g stone. I can work it out for an additional 4th bedroom. Phase 3 has 3 bedrooms. Feel free to pop in any time .